Project Schedule
The following schedule outlines the timing of planned key components within each calendar year over the contract’s duration. This schedule will be updated as the project progresses.
Year 1 (2024)
Rehabilitate Langstaff Road underpass structure
Shoulder strengthening along Highway 400 median shoulders and Langstaff Road southeast and southwest ramp
Construct permanent ramp widening and replace culverts under ramps along the west side of Highway 400 (southbound ramps)
Construct mainline culverts using trenchless installation method
Construct permanent ramp widening and replace culverts under ramps along the east side of Highway 400 (northbound ramps)
Construct outside widening, advanced traffic management system (ATMS) infrastructure and outside overhead sign footings along Highway 400 southbound
Rehabilitate Black Creek culvert
Year 2 (2025)
Rehabilitate Rutherford Road underpass structure;
Rehabilitate existing Highway 400 northbound lanes and shift the crown between existing crown and proposed widening;
Construct outside widening, ATMS infrastructure and outside overhead sign footings along Highway 400 northbound;
Reconstruct Highway 400 northbound concrete barrier separator and storm sewer system between the Langstaff Road off-ramp and the transfer lanes;
Construct HIghway 400 southbound core/collector transfer lane concrete barrier separator and storm sewer system, including storm sewer outlet, using trenchless installation method;
Rehabilitate existing Highway 400 southbound lanes and shift the crown between existing crown and proposed widening; and
Construct retained soil systems (RSS) wall south of Bass Pro Mills interchange.
Year 3 (2026)
Reconstruct median tall wall, median storm sewer system, median footings and median high mast lighting along Highway 400;
Rehabilitate existing Highway 400 lanes between existing crown and the median barrier; and
Construct overhead sign support structures and install final signage.
Year 4 (2027)
Pave the surface course asphalt and paint final pavement markings.
Existing Highway 400 in Project Area
Project Milestones
View completed project milestones:
There are currently no completed milestones.